Helm splits $55,300 job, avoids statutory bidding

CanServ installs system on same day, but purchase orders show differently

CLAREMORE — Purchase order issues continue to surface for Rogers County Commissioner Mike Helm as $55,300 in purchases from CanServ LLC of Tulsa were made without following proper bid procedures.

To complicate matters some of the purchase orders were not encumbered prior to the receipt of the product which is required by state statute.
Scrutiny centers on purchase orders for the installation of a Lincoln Lube system that self-lubricates moving parts on a variety of construction equipment.
Work was done multiple times by a single vendor during the same month and even during the same day. 
However, the vendor’s quote was split into separate purchase orders. Helm received a single quote with an itemized list prior to the completion of the work and had advance knowledge that the project would exceed the $10,000 limit. When questioned Helm said that it was broken down for each piece of equipment.
“It is a project they can’t do them all at the same time,” Helm said. “We call them and have them do them when the equipment is ready.”
Helm also added that they are provided with a quote when the company comes to the barn to the do the work.
CanServ employee Ty Richardson quoted prices for a Lincoln Lube system for six different pieces of equipment on March 9, 2012, according to Helm’s email. 
The document received by the Claremore Progress by Open Records request details the cost and options for each piece of equipment, including different pricing options depending on work that would be done during installation.
The vendor records for the CanServ job have been provided to Rogers County District Attorney Janice Steidley by the Claremore Daily Progress.
For example, a John Deere 872 motor grader with braded lines and fittings would be $10,300 for installation.
Each item was presented in the same manner and six items were included in the quote.
The total expected price, according to the quote was approximately $55,300, depending on additional hose or braided line that would be needed at the time of installation.
Statutes require all purchases that exceed $10,000 to be competitive bid. In this case Helm did not put out the installation for competitive bid, despite CanServ’s quote of $55,300.
Each installation was completed and listed on a separate invoice, even though the work was included in a single quote for the same system.
Title 19 of the state statute states that “splitting purchases for the purpose of avoiding competitive bidding and paying an amount in excess of [$10,000] is prohibited. Any persons convicted of violating this provision will be guilty of a misdemeanor and will forfeit their position or office.”
Oklahoma State Auditor and Inspector Gary Jones interprets the bid limit mentioned above, to mean that the expenditure of more than the bid limit within a year (not necessarily a fiscal year) for the same item, service, system, etc. would be a violation of this provision and would constitute splitting purchase orders under most circumstances.
Helm said when asked about following bidding procedures. “I can not explain why there was a shortfall. I wait until they give me a quote.”
CanServ sent representatives out on multiple dates to complete the work.
The first installation was completed on April 5, 2012 and purchase order 207229 for $9,800.
Two other installations were completed during the month of April 2012, according to purchase order 207848 for $7,800 and purchase order 207747 for $9,800.
These two systems were installed on April 13 for a total cost of $17,600.
The work orders provided by CanServ to the Claremore Progress show details of the transaction, including a change to the invoice number.
It appears the invoice number was changed to reflect two separate invoices, despite the work being done on the same day.
Additionally, Helm’s department filed the purchase orders almost a week apart with the receiving reports reflecting different dates, yet both items were completed on the same day. 
Two more purchase orders were submitted for payment in May and June, however both of the systems were installed in May.
Purchase order 209090 for $9,500 is dated June 6, yet the work was completed on May 21. Purchase order 208258 for $9,800 was completed on May 3.
Instead of filing one invoice for the work totally $19,300 the work was filed in two separate months.
The final installation submitted for payment was purchase order 301264 for $9,500. It was submitted on Aug. 13.
Helm said that the systems were installed as part of a maintenance and safety issue.

Text Only
Government
  • Claremore hosts dump day June 1
    The City of Claremore will host a dump day for residents from 8 a.m. to noon on June 1 at several locations.
    The event is a public service for residents sponsored by the city and Cherokee Nation CRC, according to Stormwater Manager Charlene Lawrence.

    May 18, 2013

  • Click It or Ticket: Claremore PD to take part in national mobilization

    The Claremore Police Department will participate in the annual “Click It or Ticket” mobilization set for Monday through June 2. 

    May 17, 2013

  • UPDATE: Recent county tax vote could be invalid

    Voters went to the polls on Tuesday passing the renewal of the Rogers County One-Cent Sales Tax, however doubts over legal publication of the election are creating concern that the election could be invalid.

    May 16, 2013

  • Deadline extended for tax exemptions

    Rogers County Assessor Scott Marsh is extending the deadline to May 31 for residents to file tax exemption due to the move to the new building.

    May 16, 2013

  • County says yes to tax renewal

    The Rogers County One-Cent sales tax has been renewed after voters took to the polls Tuesday in small numbers to support the measure.

    May 14, 2013

  • County outsources safety training to NTC

    The Rogers County Commissioners approved Monday the outsourcing of safety training to Northeast Technology Center  in an effort to provide better quality training to employees.

    May 14, 2013

  • Rep Marty Quinn Sen. Burrage, Rep. Quinn give updates

    Elected officials updated city leaders on issues currently facing state and local governments Friday at the Will Rogers Museum Memorial.

    May 13, 2013 2 Photos

  • County audit underway
    The office of Oklahoma State Auditor Gary Jones started a general audit of Rogers County this week.
     

    May 12, 2013

  • JM Davis closures J.M. Davis project prompts road closure

    A portion of a busy Claremore street will close Tuesday for a widening project.

    May 10, 2013 1 Photo

  • BNSF railway crossings BNSF schedules upgrades at 3 crossings

    Rogers County Commissioner Dan DeLozier is planning for the temporary closure of three area railroad crossings while BNSF Railway crews complete crossing upgrades.

    May 10, 2013 1 Photo